Case Studies

Results that speak

A selection of anonymized project summaries demonstrating our track record of successful claim recovery, project controls implementation, and dispute resolution across the GCC and internationally.

Delay Claim — KSA

Infrastructure Mega-Project

Prepared a comprehensive TIA delay claim for a 36-month infrastructure project impacted by design changes, access restrictions, and employer-caused delays.

285 days
Extension of time awarded
Quantum Claim — UAE

Commercial Tower

Quantified prolongation and disruption costs for a high-rise contractor impacted by late design approvals and concurrent delays across multiple packages.

$8.2M
Recovered in prolongation costs
Project Controls — KSA

Oil & Gas Facility

Implemented a complete project controls framework including baseline scheduling, EVM, and risk management for a $450M greenfield facility.

On time
Delivered within schedule & budget
FIDIC Advisory — Qatar

Hospitality Development

Provided ongoing contract administration for a luxury resort project, managing 120+ variations and ensuring all notices were issued within FIDIC timeframes.

$12M
In variations recovered
Expert Witness — KSA

Industrial Complex

Prepared expert delay and quantum reports for ICC arbitration involving a $180M petrochemical facility dispute. Provided oral testimony over 3 hearing days.

Favorable
Settlement achieved pre-award
Disruption Claim — UAE

Healthcare Facility

Analyzed and quantified loss of productivity using measured mile analysis for a hospital construction project impacted by design changes and congestion.

$3.8M
Disruption damages awarded